Fairhaven Home StoresStore operations improvement program
Theme
Steering
Where the four workstreams stand before the Thursday, October 8 meeting, who has to act and by when. Ask a question here and the answer stays with the item.
The steering cycle
- Workstream updates on time
- 3 of 4
- Milestones moved
- 1
- Open dependencies
- 6
- Decisions requested
- 4
shrink reduction came in a day late
replenishment pilot, Oct 2 to Oct 16
1 without a Fairhaven owner
for the Oct 8 meeting
Workstreams by status
Steering packStatus after the Sep 28 window. The program director questions a color when the evidence does not support it.
Green1
- Distribution center flowCarrier appointments confirmed for the first two wave 2 weeks. Cutover plan due Oct 16
Amber2
- ReplenishmentPilot start moved from Oct 2 to Oct 16
- Store labor schedulingTwo stores held out of the totals until their trackers match
Red1
- Shrink reductionNo agreed baseline, no owner for loss prevention data access and one change request open
The next two weeks
Dates from the program record. Your items are marked.
- Draft steering pack issuedPhilippa SinclairDone
- Today, Oct 1
- HR sign-off on the shift templateHR leadPlanned
- Planogram file for the three missing storesMerchandising managerPlanned
- Store labor trackers reconciledHamish AldousPlanned
- Final steering pack issuedPhilippa SinclairPlanned
- Name an owner for loss prevention data accessGareth PryceWaiting on you
- Store system data extract scheduledIT directorPlanned
- Decide the shrink dashboard change requestGareth PryceWaiting on you
- Replenishment pilot starts in 12 storesFairhaven store managersPlanned
Approval gates
Two are approved. Two wait for you or for the loss prevention lead.