Fairhaven Home StoresStore operations improvement program
Theme
Onboarding
The charter, workstreams, decision owners and baselines every steering pack reads from. Six of eight items are in, and the two still waiting both sit with Fairhaven.
- Program charterAgreed in June
- Workstreams and milestonesFour streams, one date moved
- Governance and decision ownersOne owner to name
- BaselinesShrink baseline open
Program onboarding
The four onboarding steps with every item, owner and date. Tick items off as your team sends them.What is still open
What onboarding needs
Access is requested at the minimum each task needs and recorded here. You can revoke any grant.
| Item | Step | Status |
|---|---|---|
| Program charter and scope for each workstream | Program charter | Agreed |
| Milestones and dates for the four workstreams | Workstreams and milestones | Agreed |
| Replenishment pilot start date | Workstreams and milestones | Re-dated to Oct 16 |
| Steering group and decision owners | Governance and decision owners | Agreed |
| Fairhaven owner for loss prevention data access | Governance and decision owners | Waiting on you |
| Out-of-stock baseline, 7.4 percent in June | Baselines | Agreed |
| Scheduled labor hours baseline, 104 percent | Baselines | Agreed |
| Shrink baseline | Baselines | Waiting for the loss prevention lead |