What Ferncastle needs from Fairhaven, why, and by when. Upload straight into the request.
- Shift template sign-off from the HR leadHR lead. It holds up the labor scheduling pilot, and no sign-off date has been given yet.Due Oct 5
- Planogram file for the three missing pilot storesMerchandising manager. The August file covered 9 of the 12 pilot stores.Due Oct 6
- Labor tracker exports for the two held-out storesRegional operations manager and both store managers. Hamish reconciles them against the program record.Due Oct 7
- Schedule for the store system data extractIT director. The first daily extract of store stock positions. The Oct 16 pilot date holds only if it is scheduled.Due Oct 9
- Approval to request loss prevention system accessNeeds a Fairhaven owner first. Philippa has the request drafted.No owner yet
- Weekly store results for the 12 pilot storesReceived for the week of Sep 21 and loaded into the program record.Received