Fairhaven Home StoresStore operations improvement program

Theme
Ask Philippa

Decisions and actions

What the steering group decided on Sep 24, and where each of the four decisions stands on Sep 28: the actions it became, who owns them and when they are due.

Decision log, updated Oct 1, 2026
A sponsor and a PMO analyst reviewing steering decisions

The four decisions of September 24

Steering meeting of Sep 24, 2026 State on Sep 28 Three shift template actions not started

What the steering group decided on Thursday, September 24, 2026, and where each of the four decisions stands on Monday, September 28: the actions it became, who owns them and when they are due. Kept by Emeka Achebe, PMO analyst at Ferncastle Operations Group, and reviewed by Philippa Sinclair, program director, for Gareth Pryce, chief operating officer at Fairhaven Home Stores, and the workstream leads. The rule of the log is simple: every decision turns into owned workstream actions within two days, and a decision still waiting for an owner is shown as such, not hidden.

Decisions taken on Sep 244all four now Owned
Workstream actions from them143 decisions gave 11, the fourth gave 3
Actions done55 more in progress
Actions not started43 shift template, 1 shrink baseline

Each decision shows its owner, the Fairhaven owner and the actions it became. Owned means a named person has accepted it. The two day mark for each decision was Sep 26.

DecisionWorkstreamOwnerFairhaven ownerStatusActions from it
Reset the replenishment pilot date to Oct 16ReplenishmentPhilippa SinclairGareth PryceOwned4 actions: 2 closed, 2 in progress
Pilot the new shift template in eight storesStore labor schedulingEmeka AchebeRegional operations managerOwned Sep 26 Not started3 actions, none started
Hold two stores out of the labor totalsStore labor schedulingPhilippa SinclairGareth PryceOwned2 actions: 1 closed, 1 in progress
Plan wave 2 and the shrink baseline for NovemberDistribution center flowHamish AldousGareth PryceOwned5 actions: 2 closed, 2 in progress, 1 not started
Live from the Dashboards appOpen the full report

Decisions and their actions

Each steering decision is listed with the actions linked to it, and the sections further down show every action by workstream. Read the Status column for actions that are Owned but not started, and the Due column for those due before the Oct 8 steering meeting. The log holds 18 rows: the four decisions and their 14 actions.

Did every decision get an owner in two days?

The squares below show the state two days after the meeting: three decisions had owned actions within two days, and one was still waiting for an owner, which was named later. The one waiting was the shift template pilot. Gareth Pryce then named the regional operations manager as its owner on Sep 26, so the table above, which is the state on Sep 28, shows all four as Owned.

"I had not named a store operations owner in the room. Seeing the decision sit there with no one against it is what made me name one the same week."

Gareth Pryce, Chief operating officer, Fairhaven Home Stores

Live from the Dashboards appOpen the full report

Where the 14 actions stand

All 14 actions from the four decisions are counted by workstream and status. Five are done, five are in progress and four are not started. Store labor scheduling carries three of the four that have not started.

Replenishment

Decision: Reset the replenishment pilot date to Oct 16. Owner: Philippa Sinclair.

ActionOwnerFairhaven ownerDueStatus
Agree the new pilot date with the 12 pilot storesEmeka AchebeRegional operations managerSep 29Closed
Update the replenishment rules calendarSaoirse QuigleyMerchandising managerSep 30Closed
Re-run the store stock test on the extract sampleSaoirse QuigleyIT directorOct 12In progress
Brief store managers on the Oct 16 startEmeka AchebeRegional operations managerOct 9In progress

Store labor scheduling

Decisions: Hold two stores out of the labor totals (Philippa Sinclair) and Pilot the new shift template in eight stores (Emeka Achebe).

ActionOwnerFairhaven ownerDueStatus
Exclude the two stores from the pack totalsEmeka AchebeGareth PryceSep 25Closed
Reconcile the two store labor trackersHamish AldousRegional operations managerOct 7In progress
Choose the eight pilot stores for the shift templateEmeka AchebeRegional operations managerOct 9Owned
Train store managers on the shift templateEmeka AchebeRegional operations managerOct 16Owned
Set the review measure for the shift templatePhilippa SinclairRegional operations managerOct 16Owned

Shrink reduction

Decision: Plan wave 2 and the shrink baseline for November. Owner: Hamish Aldous.

ActionOwnerFairhaven ownerDueStatus
Request loss prevention system accessPhilippa SinclairNone yetOct 9In progress
Draft the shrink baseline methodSaoirse QuigleyLoss prevention leadOct 23Owned

The access request is drafted but needs a Fairhaven owner to approve it. The baseline method starts once access is granted.

Distribution center flow

Decision: Plan wave 2 and the shrink baseline for November. Owner: Hamish Aldous.

ActionOwnerFairhaven ownerDueStatus
Confirm wave 2 carrier appointmentsHamish AldousDC operations managerSep 30Closed
Map wave 2 receiving doorsSaoirse QuigleyDC operations managerSep 30Closed
Plan the wave 2 cutover weekendHamish AldousDC operations managerOct 16In progress
Live from the Dashboards appOpen the full report

From decision to action

How each decision of Sep 24 reached its actions, and where one of them waited:

DecisionActions it becameWhere it waited
Reset the replenishment pilot date to Oct 164 actions: 2 closed, 2 in progressNowhere. Owned within two days
Pilot the new shift template in eight stores3 actions, owned and not startedThree actions sat unassigned until the regional operations manager was named on Sep 26
Hold two stores out of the labor totals2 actions: 1 closed, 1 in progressNowhere. Owned within two days
Plan wave 2 and the shrink baseline for November5 actions: 2 closed, 2 in progress, 1 not startedNowhere. Owned within two days
Two day rule
Every decision is turned into owned actions within two days of the meeting. Each decision and action names a Ferncastle owner and a Fairhaven owner.
Missing owner
A missing owner is shown as missing and never filled in. Request loss prevention system access shows no Fairhaven owner for that reason.
Owned
A named person has accepted the decision or action. For an action, work has not started yet.
Closing an action
An action closes when its owner confirms the result, with the evidence in the record.

Check before the next steering meeting

Before Thursday, October 8

  • Check the three shift template actions are underway. Owner: Emeka Achebe, before Oct 8open
  • Reconcile the two store labor trackers with both store managers. Owner: Hamish Aldous, Oct 7open
  • Check the four replenishment actions at the steering meeting. Owner: Philippa Sinclair, Oct 8open
  • Review the five wave 2 and shrink baseline actions at the steering meeting. Owner: Hamish Aldous, Oct 8open
  • Send the loss prevention access request once a Fairhaven owner is named. Owner: Philippa Sinclair, Oct 9open
  • Exclude the two stores from the pack totals. Owner: Emeka Achebe, donedone
  • Name an owner for the shift template decision. Owner: Gareth Pryce, done Sep 26done

Who keeps this log

  • Emeka AchebePMO analyst, Ferncastle Operations Group, keeps the log and raised the owner gap

  • Philippa SinclairProgram director, Ferncastle Operations Group, reviews the log

  • Gareth PryceChief operating officer, Fairhaven Home Stores, takes the decisions

The live page in FuseBase

This document as a FuseBase page, read-only from the Ferncastle Operations Group workspace. Changes made there appear here.
Open the page